KBR Inc. has been awarded a four-year contract by South Australian Water Corp. (SA Water) to support the utility's capital delivery program, which the company describes as one of the South Australian Government's most significant infrastructure programs. KBR is headquartered in Houston, Texas; SA Water is based in Adelaide.
The agreement covers a period in which SA Water plans about A$3.3 billion of water infrastructure investment over four years, described as the utility's largest-ever period of investment. KBR won the work through a competitive tender, extending a 15-year partnership with SA Water through 2030.
Under the contract, KBR will support delivery of water and wastewater infrastructure for SA Water's 1.8 million customers across South Australia. The scope outlined by the company includes dam upgrades, water tank refurbishments, bulk water transfer infrastructure, water main replacements, sewer network upgrades, and upgrades to water and wastewater treatment plants.
KBR's contribution covers design, delivery and project management support, according to the company, and the new term carries that role into the utility's forward capital program.
The capital delivery team has handled more than 2,000 individual projects over the past year, KBR said. Those included 69 kilometers of new water mains, a major upgrade of the 132-kilometer Tailem Bend to Keith pipeline, and a desalination plant serving the outback town of Marree.
Programs ahead
Work identified for the next four years includes:
- South Australia's Housing Roadmap, which calls for expanding water and wastewater networks to support an estimated 50,000 new homes across the state;
- Infrastructure delivery such as upgrades to the Morgan to Whyalla pipeline, South Australia's longest water pipeline at 358 kilometers.
Company view
Margaret Riley, KBR's director of water, said the appointment reinforces the company's position as a trusted partner in the water sector.
Riley said KBR was proud to be selected again by SA Water to continue supporting the capital delivery program, adding that the company had worked alongside the utility over the past 15 years to design, deliver and project manage some of the most critical water infrastructure projects. She described the contract as a demonstration of the team's experience, technical capability and focus on safety, innovation and service excellence, and said KBR looks forward to working closely with SA Water to deliver lasting benefits for customers, communities and the broader South Australian economy.
The four-year term carries the relationship, which KBR says now runs through 2030, into the utility's largest investment period. Commercial terms were not disclosed.