A U.S. Department of Energy emergency order directing PJM Interconnection to use additional generating resources should serve as a warning for Michigan and the wider PJM region, according to a sponsored commentary published by Solar Mounts LLC.
The order, dated Oct. 12, 2026, took effect Oct. 13–16. It authorizes specified power plants to operate as needed for reliability and allows backup generators at large facilities to help reduce grid demand during emergencies, the commentary said.
Terence Parker, a Michigan resident and Solar Mounts team member, wrote that the directive does not mean blackouts are inevitable. It does, however, highlight the challenges facing the electricity system and the need to add capacity before emergency measures become routine, he said.
Capacity prices signal pressure
The commentary pointed to PJM capacity auctions as evidence of difficulty securing enough electricity for future demand. Prices reached $329.17 per megawatt-day for the 2026–2027 delivery year and $333.44 for 2027–2028, according to the piece, which cited Vicinity Energy’s analysis. The later auction fell short of PJM’s stated reliability requirement, the commentary said.
Capacity costs are only one part of electricity bills, but rising prices signal growing pressure on consumers, Parker wrote. He argued that more power is needed before shortages force increasingly expensive emergency responses.
The order permits designated generating units to exceed specified operating limits when necessary for reliability. It also authorizes PJM to direct backup generation at data centers and other large facilities, potentially including diesel generators as a last resort, according to the commentary.
Running fossil-fuel plants more frequently can increase emissions depending on the units involved, the piece said. Operating diesel generators would worsen local noise pollution and expose operators to high diesel prices, it added. If such measures become more common, Parker wrote, the question is why cleaner generation and storage are not coming online faster.
Weather and demand uncertainty
The commentary also cited NOAA’s Oct. 15, 2026, winter outlook, which anticipates warmer-than-average conditions across much of the northern United States, including the Midwest, influenced by a strong El Niño. Seasonal forecasts cannot predict every period of extreme demand, the piece said, and aging infrastructure, maintenance, changing weather and growing electricity consumption reinforce the need for advance planning.
Utility-scale solar, wind and battery storage can help meet demand on timelines many conventional generation projects cannot match, according to Solar Mounts. Suitable solar projects may be built within 18 months, depending on permitting, equipment and interconnection, the commentary said. New nuclear facilities generally require substantially longer development periods.
Solar and wind reduce emissions when they displace electricity from fossil-fuel generators, and batteries store surplus power for higher-demand periods, the piece said. Actual emissions benefits depend on which generators are displaced and when electricity is delivered.
Faster interconnection reviews are essential, Parker wrote. Qualified solar projects should not remain in queues for years because of avoidable administrative delays, and better coordination among PJM, utilities, regulators, developers and state governments, along with necessary transmission upgrades, would bring capacity online sooner, he said.
Land use and data-center demand
The commentary addressed concerns about installing solar on productive farmland in rural Calhoun County, where Solar Mounts is based. Well-designed projects can include restoration plans that allow agricultural use to resume when leases end, according to the company, and solar leases can provide farmers with supplemental income when crop prices fail to keep pace with production costs.
Agrivoltaic systems combine electricity generation with compatible crops or livestock, the piece said. Thoughtful design and community engagement can balance renewable development with agricultural productivity, rural traditions and farmland preservation, according to the commentary. It also pointed to parking lots, commercial properties, brownfields, landfills and other underutilized sites, as well as solar carports and community solar.
Growing data-center demand, particularly in Virginia and other parts of PJM’s territory, is adding pressure to an already constrained grid, the commentary said. Developers of new hyperscale facilities should demonstrate how they will secure adequate electricity and pay their fair share of supporting infrastructure, it argued. Dedicated generation, renewable energy contracts, batteries, flexible demand and grid upgrades can all contribute.
Requiring every facility to build a gas-fired peaker plant is not necessarily the best answer, according to the piece. Gas turbines face equipment and supply-chain constraints, while additional fossil-fuel generation carries emissions and operating costs, it said. A combination of solutions tailored to each location is more practical, and existing facilities should reduce peak demand where possible.
Solar Mounts said it supports faster approvals, better grid planning and a serious commitment to adding generation and storage before shortages worsen. Repeated emergency orders, rising capacity costs and greater reliance on high-emission generation are not sound long-term strategies, the commentary concluded.